2015-05-07 - 16728 - Rel Notes - SNC Single Work Order Process #SAPReleaseNotes

Release Notes - Draft

6474 : SNC Single Work Order Scenario

Admin Info



Purpose
SNC Single Work Order Scenario
Release No
001
Submitted on
05/07/2015
Submitted by
Adithya
Environment
NED/SND to NEQ/SNQ
Sent To
Jeffrey Mau, Saravanan
Object(s) created by
Venkat, Damodhier
Object(s) tested by
Adithya
Transport Status
Created in NED300 / 100 & SND 100
Transport and Technical Objects

Sl.
Transport ID
Description
Object Name
1
NEDK929872
SNC : 16728 : MASS Copy confirmations for all PO lines
ZPO_CONFIRMATION
2
SNDK900432
SNC:16728: Work List Creation for Single WO
ZNEC_WO_WL_CREATE_SINGLE
Release Notes

For Infrastructure


For Requester



The objects included in this release support all scenarios for POs where no changes have been made after publishing.

Test scenarios where PO lines have been changed/deleted after the publish confirmation step are not included in this release.


Test Notes

System : NED300/SND100

Test ID
Test Scenario
Expected Results
Actual Results
P/F
Documents
Notes
Tested By
QA By
SNC001
End to end cycle for order type NB without any line deletions.
1. Outputs and document data match current multi WL process

2. Work Orders shall be created one per each PO line Item but the work list is to be created only for the first active line.
3. The Confirmations shall be copied to all the lines of the PO.
1. Outputs and document data matched current multi WL process
2. Work Orders are created one per each PO line Item and the work list is created only for the first active line.
3. The Confirmations shall be copied to all the lines of the PO.
P
4600007935

Adithya
Adithya
SNC002
End to end cycle for order type NB without any line deletions for large POs
1. Outputs and document data match current multi WL process

2. Work Orders shall be created one per each PO line Item but the work list is to be created only for the first active line.
3. The Confirmations shall be copied to all the lines of the PO.
1. Outputs and document data matched current multi WL process
2. Work Orders are created one per each PO line Item and the work list is created only for the first active line.
3. The Confirmations shall be copied to all the lines of the PO.
P
4600008097
4600008098
4600008087
4600008099

Adithya
Adithya
SNC003
End to end cycle for order type Z3NB without any line deletions.
1. Outputs and document data match current multi WL process

2. Work Orders shall be created one per each PO line Item but the work list is to be created only for the first active line.
3. The Confirmations shall be copied to all the lines of the PO.
1. Outputs and document data matched current multi WL process.
2. Work Orders are created one per each PO line Item and the work list is created only for the first active line.
3. The Confirmations shall be copied to all the lines of the PO.
P
4600007947

Adithya
Adithya
SNC004
End to end cycle for order type Z3NB without any line deletions for large POs.
1. Outputs and document data match current multi WL process

2. Work Orders shall be created one per each PO line Item but the work list is to be created only for the first active line.
3. The Confirmations shall be copied to all the lines of the PO.
1. Outputs and document data matched current multi WL process

2. Work Orders are created one per each PO line Item and the work list is created only for the first active line.
3. The Confirmations shall be copied to all the lines of the PO.
P
4600008092
4600008094
4600008095
4600008096

Adithya
Adithya
SNC005
Run Program ZPO_CONFIRMATION with some deleted line in a PO
Outputs and document data match current multi WL process
The Confirmation is not updated on the deleted line.
P
4600008139

Adithya
Adithya
SNC006
Mass Update Program - Validate it works for all non deleted lines only.
Outputs and document data match current multi WL process
The work orders are created for all the active lines of the PO and the Work list must be updated for the first active line which is line 30.
P
4600008139
Line 10 & 20

Adithya
Adithya
SNC006
End to end cycle for order type NB-TAB without any line deletions.
1. Outputs and document data match current multi WL process

2. Work Orders shall be created one per each PO line Item but the work list is to be created only for the first active line.
3. The Confirmations shall be copied to all the lines of the PO.
1. Outputs and document data matched current multi WL process

2. Work Orders are created one per each PO line Item and the work list is created only for the first active line.
3. The Confirmations shall be copied to all the lines of the PO.
P
4600007943

Adithya
Adithya
SNC008
End to end cycle for order type NB-TAB without any line deletions for large POs
1. Outputs and document data match current multi WL process

2. Work Orders shall be created one per each PO line Item but the work list is to be created only for the first active line.
3. The Confirmations shall be copied to all the lines of the PO.
1. Outputs and document data matched current multi WL process
2. Work Orders are created one per each PO line Item and the work list is created only for the first active line.
3. The Confirmations shall be copied to all the lines of the PO.
P
4600008135
4600008136
4600008137

Adithya
Adithya

End to end steps with NB Order Type:
Create a PO
Move to SNC
Print ECC PO
PO Download ECC
Publish PO
Create INB delivery
Create WO
Publish WO
Create WO WL
Update confirmations till ZN
Copy Status for all lines of PO
Create ASN Per SO (Draft)
Update ZP
Update the Data in ASN and Save draft
Publish ASN (Final)
MIGO the PO

End to end steps with Z3NB Order Type:
Create a PO
Move to SNC
Publish PO
Create WO
Publish WO
Create WO WL
Update confirmations till ZN
Copy Status for all lines of PO
Create INB delivery
Pack the INB delivery
Print UCC labels
Drop Ship Carton Label - SNC 170
Update ZP
Create ASN Per SO (Draft)
Update the Data in ASN and Save draft
ZASN Forward (Booking & Shipping)
Publish ASN (Final)
Create PGR for INB Delivery
ASN From PGR

System: NECNEQ100



Test ID
Test Scenario
Expected Results
Actual Results
P/F
Documents
Notes
Tested By
QA By




















Reference Document (Specification or Production Support Break Fix)



SCM - 2015-04-14 - 16728 - SNC Approach on Single Work Order Create for a PO (Jeff by 2015-05-29)
SCM - 2015-05-04 - 16728 - Spec - SNC Single Work Order (Jeff by 2015-05-29)